Section 24-A: Disposal of pending proceedings under Sections. 23 or 24

The Rajasthan Rent Control Act, 2001

How current this text is

Text as published by India Code for the Government of Rajasthan, with amendments up to the Rajasthan Rent Control (Amendment) Act, 2017 (Act No. 33 of 2017).

1[All the proceedings under Sec. 23 or 24 pending before the Rent Tribunal on the date of commencement of the Rajasthan Rent Control (Amendment) Act, 2017 (Act No. 33 of 2017) shall be continued and the Rent Tribunal may pass appropriate orders thereon as if Sec. 23 or 24 was not amended by the said Act]

Footnotes in the official text

  1. 1.Inserted By THE RAJASTHAN RENT CONTROL (AMENDMENT)ACT, 2017(Act 33 Of 2017) dated 27.09.2017