Section 15-A: Completion certificate

The Uttar Pradesh Urban Planning and Development Act, 1973

How current this text is

Text as published by India Code for the Government of Uttar Pradesh, with amendments up to U.P. Act No. 1 of 2025.

The Act was made as President's Act No. 11 of 1973; this copy shows the enacting words substituted by U.P. Act No. 30 of 1974, and the Reasons for the Enactment printed after section 60 are not reproduced.

The marginal headings printed beside each section in this edition are shown as the section headings; section 60 carries no marginal heading in this copy.

1[(1) Every person ro body having been granted permission under sub-section (3) of section 15, shall complete the developments according to the approved plan and send a notice in writing of such completion to the Authority, and obtain a completion certificate from the Authority in the manner prescribed or provided in the Bye-laws of the Authority.

Provided that if completion certificate is not granted and refusal to grant it is not intimated within three months after receipt of the notice of completion, it shall be deemed that the completion certificate has been granted by the Authority.

(2) No person shall occupy or permit to be occupied any commercial building or use or permit to be used such building or part thereof affected by any work until—

(a) completion certificate has been issued by the Authority, or

(b) Authority has failed for three months after the receipt of the notice of completion to intimate its refusal of grant of the said certificate.

Explanation:— For the purposes of this section the expression "commercial building" shall have the meaning assigned to it in the Uttar Pradesh Municipal Corporations Act, 1959.]

Footnotes in the official text

  1. 1.Ins. by sec. 4 of U. P. Act No. 03 of 1997.

Practise questions on Uttar Pradesh Local Laws