The Real Estate (Regulation and Development) Act, 2016 (RERA) protects homebuyers by making promoters register projects before selling them, park seventy per cent of buyers' money in a separate project account, stick to sanctioned plans, and either refund with interest or pay monthly interest when possession is delayed. Complaints go to the state Real Estate Regulatory Authority, compensation claims to its adjudicating officer, and appeals to the Real Estate Appellate Tribunal and then the High Court. For exam answers, the same scheme reduces to a handful of sections: 3, 4, 13, 14, 18, 19, 31, 43, 71, 79 and 88.
What does RERA regulate, and when did it come into force?
RERA regulates the sale of plots, apartments and buildings in real estate projects by promoters, and the work of real estate agents, through a regulatory authority in each state or union territory. It came into force in two stages: definitions, the authorities and the tribunals from 1 May 2016, and the operative obligations in sections 3 to 19, along with the penalty and civil court bar provisions, from 1 May 2017.
Three definitions decide most questions. A promoter, broadly, is anyone who constructs or develops a project for sale, including a development authority; where the person who builds and the person who sells are different, both are treated as promoters. An allottee, under section 2(d), is the person to whom a plot, apartment or building has been allotted, sold or otherwise transferred by the promoter, including a subsequent purchaser of that allotment, but not a tenant. And an apartment includes offices, shops and godowns, so RERA is not limited to homes.
Which projects must be registered under section 3?
A promoter cannot advertise, market, book, sell or offer for sale any plot, apartment or building in a project within a planning area without first registering the project with the Authority, under section 3. Projects ongoing on 1 May 2017 without a completion certificate also had to be registered within three months.
Registration is not required where:
- the land to be developed does not exceed 500 square metres, or the apartments do not exceed eight, counting all phases (states may lower these thresholds);
- the promoter had a completion certificate before the Act commenced;
- the work is renovation, repair or redevelopment that involves no marketing, sale or new allotment.
Each phase of a phased project is treated as a separate project needing its own registration. Selling without registration attracts a penalty of up to ten per cent of the estimated project cost under section 59, and continued violation can lead to imprisonment up to three years, a further fine of up to ten per cent, or both.
How does RERA protect the buyer's money and the agreed plan?
Four provisions do most of the protective work before possession.
| Protection | What it requires | Section |
|---|---|---|
| Separate account | 70% of amounts realised from allottees deposited in a separate scheduled bank account, used only for land and construction cost, withdrawn in proportion to completion on certificates of an engineer, architect and chartered accountant | s.4(2)(l)(D) |
| Cap on advance | No more than 10% of the cost taken as advance or application fee before a written agreement for sale is executed and registered | s.13(1) |
| No unilateral changes | No changes to the sanctioned plan or specifications of a buyer's unit without that buyer's consent; no other changes to the building or common areas without written consent of two-thirds of allottees | s.14(2) |
| Defect liability | Structural and workmanship defects reported within five years of possession must be rectified free within thirty days, failing which compensation follows | s.14(3) |
The ten per cent rule in section 13 is a common trap. Suppose a buyer pays fifteen per cent of the price as a "booking amount" on a receipt, and the builder delays the agreement for sale. The promoter has already contravened section 13; the agreement for sale must be in writing and registered before any amount beyond ten per cent is accepted. Buyers reading a draft before signing can compare its clauses with a standard agreement to sell template on LegalDrive, though a RERA agreement for sale must also follow the form prescribed by the state rules.
For the two-thirds rule in section 14(2)(ii), an allottee counts as one person however many units he or his family or group entities have booked, so a promoter cannot manufacture consent through related buyers.
What can a homebuyer claim when possession is delayed?
When a promoter fails to complete the project or hand over possession by the date in the agreement for sale, section 18 gives the allottee a choice:
- Withdraw from the project: the promoter must, on demand, refund the full amount received with interest at the prescribed rate, plus compensation as provided under the Act.
- Stay in the project: the promoter must pay interest for every month of delay until possession is handed over.
The same liability arises if the promoter discontinues business because its registration is suspended or revoked. Section 18(2) adds compensation for loss caused by a defective title to the land, and expressly says that claim is not barred by limitation. Section 18(3) covers failure of any other obligation under the Act or the agreement.
The buyer also has duties under section 19: to pay instalments on time, to pay the share of registration charges, taxes and maintenance, and to pay interest at the prescribed rate on his own delays. Exam problems sometimes test whether a buyer who defaulted on instalments can still claim delay interest; the answer depends on whether the promoter's delay was caused by the buyer's default, and the interest obligations run both ways.
Suppose a buyer booked a flat in 2019 with possession promised by December 2022, paid every instalment, and in 2026 the tower is still incomplete. If she still wants the flat, she claims interest for each month from January 2023 until possession. If she has lost faith in the project, she can withdraw and claim a refund of everything paid, with interest at the rate prescribed in the state rules, plus compensation for her loss, which is assessed by the adjudicating officer.
Where does the homebuyer file, and how do appeals work?
Complaints about any contravention go to the Authority or the adjudicating officer under section 31, and an association of allottees or a registered voluntary consumer association can also file. The forums divide the work in a way students often get wrong.
| Forum | Decides | Provision |
|---|---|---|
| Real Estate Regulatory Authority | Registration, refunds and interest under s.18, penalties, directions to promoters | ss.31, 34 to 38 |
| Adjudicating officer (a serving or retired District Judge) | Compensation under ss.12, 14, 18 and 19, considering gain to the promoter, loss to the buyer and repetition | ss.71, 72 |
| Real Estate Appellate Tribunal | Appeals within 60 days from the Authority or adjudicating officer | ss.43(5), 44 |
| High Court | Appeal within 60 days on the grounds in section 100 CPC | s.58 |
In Newtech Promoters and Developers v. State of U.P. (2021), the Supreme Court held that the Act applies to projects that were ongoing when it commenced, that the Authority itself can direct refund with interest under section 18, and that compensation is for the adjudicating officer under sections 71 and 72. It also upheld the pre-deposit condition in the proviso to section 43(5): a promoter's appeal will not be entertained unless it first deposits at least thirty per cent of the penalty, or the whole amount payable to the allottee including interest and compensation, as the case may be.
The practical sequence for a buyer facing delay:
- Collect the allotment letter, agreement for sale, payment receipts and the promoter's registration details from the state RERA website.
- Write to the promoter seeking possession or refund, giving a date.
- File a complaint before the Authority in the prescribed form, choosing refund with interest or interest for delay.
- File a separate application before the adjudicating officer if seeking compensation.
- Execute the order through the Authority if the promoter does not pay; continued non-compliance attracts daily penalties under sections 63 and 64.
How does RERA sit with consumer commissions and the IBC?
RERA bars civil courts but not consumer commissions. Section 79 excludes civil court jurisdiction over matters the Authority, adjudicating officer or Tribunal can decide, while section 88 says the Act is in addition to, and not in derogation of, other laws. Relying on section 88, the Supreme Court held in Imperia Structures Ltd. v. Anil Patni (2020) that a buyer can still file a complaint under the consumer protection law; RERA is an additional remedy, not an exclusive one. The Consumer Protection Act, 2019 therefore remains open, and the public guide on filing a consumer complaint shows that route.
Homebuyers are also financial creditors under the Insolvency and Bankruptcy Code. In Pioneer Urban Land and Infrastructure v. Union of India (2019), the Court upheld that status and held that RERA and the Code operate concurrently, with the Code prevailing in case of conflict. Since 2020, allottees of a project can start insolvency against the promoter under section 7 of the IBC only jointly, with at least one hundred allottees of the same project or ten per cent of them, whichever is less.
How should RERA be written in an exam answer?
Judiciary and LLM questions on RERA usually come as short notes or problem questions on delayed possession. A strong answer names the forum, the section and the relief in that order: the Authority under section 31 for refund or interest under section 18, the adjudicating officer under section 71 for compensation, the Tribunal under section 43(5) for appeals with the promoter's pre-deposit, and section 88 with Imperia Structures for the consumer forum alternative.
Common mistakes:
- saying the adjudicating officer decides refunds, when after Newtech the Authority directs refund and interest;
- treating RERA as barring consumer complaints because of section 79;
- forgetting the ten per cent advance cap in section 13;
- quoting the 500 square metre or eight apartment exemption as "either 500 square metres and eight apartments" instead of "500 square metres or eight apartments";
- describing the defect liability period as running from the agreement date rather than from possession.
This is general information, and a lawyer should be consulted for a specific case; buyers can put their facts to a verified advocate through the property law section of Ask a Lawyer.
Key points to remember
- No sale or advertising without registration under section 3, unless the project is within 500 square metres or eight apartments.
- Seventy per cent of buyers' money must sit in a separate account and be withdrawn in proportion to completion.
- No more than ten per cent can be taken before a registered agreement for sale (section 13).
- On delay, the buyer chooses between refund with interest and compensation, or monthly interest until possession (section 18).
- The Authority orders refunds and interest; the adjudicating officer assesses compensation (Newtech, 2021).
- A promoter's appeal needs a pre-deposit of at least thirty per cent of the penalty or the full amount due to the allottee.
- RERA is additional to consumer remedies (section 88, Imperia Structures) and works alongside the IBC (Pioneer Urban).
- Structural defects reported within five years of possession must be fixed free within thirty days.
Where to go next
Read sections 3 to 19 and 31 to 44 on the RERA bare act page, then use the Consumer Protection Act mock tests to revise the consumer side of the overlap.