Facts
The appellant had four road maintenance contracts under the Kerala State Transport Project. The contract provided for reference of the Engineer's decisions to an Adjudicator and then, within 28 days, to arbitration. The Adjudicator decided four payment disputes, two each way. After 28 days, the State wrote that it would refer dispute No. 1 to arbitration and appointed its arbitrator; the appellant nominated its own, stating that it would raise all issues if the Adjudicator's decision were reopened. Before the tribunal the State sought to have the entire adjudication declared void. The tribunal held all four disputes open and decided them for the appellant. The District Judge set the award aside under Section 34. The High Court in appeal held that the tribunal, appointed at the State's request on dispute No. 1 alone, exceeded its jurisdiction because the appellant had issued no Section 21 notice of its own.
Questions before the Court
- Whether the High Court was right that the Arbitral Tribunal was appointed only to decide dispute No. 1.
- Whether the appellant's failure to issue a notice under Section 21 of the Arbitration and Conciliation Act for disputes Nos. 2 to 4 barred it from pursuing those claims before the tribunal.
What the Court held
- The State's own conduct, in invoking arbitration after the 28 day period, refusing to treat the Adjudicator's decision as final and asking the tribunal to declare the whole adjudication void, threw the entire dispute open. Following M.K. Shah Engineers, a party at fault cannot rely on non-compliance with contractual pre-arbitration steps.
- Section 21 is concerned only with fixing the commencement of arbitral proceedings for reckoning limitation. It is not a mandatory precondition, and failure to issue a Section 21 notice is not fatal if the claim is otherwise valid and the disputes arbitrable.
- The arbitration clause covered any dispute arising out of or connected with the agreement. Under Section 23 a claimant is not limited to the claims in a notice and a respondent may raise counter-claims; para 41(c) of State of Goa v. Praveen Enterprises did not apply.
- The tribunal did not exceed the scope of reference. The High Court's judgment was set aside and the award of 29.06.2006 was upheld in its entirety.
Why it matters
The judgment confirms that Section 21 is procedural and serves only to fix the date of commencement for limitation, so the absence of a separate notice from one party does not limit the tribunal's jurisdiction under a widely worded arbitration clause. It also applies the rule that a party which itself disregarded contractual pre-arbitration steps cannot rely on them to defeat the other side's claims.
In the Court's words
Copied from the official judgment; each passage links to its page.
“Section 21 is concerned only with determining the commencement of the dispute for the purpose of reckoning limitation. There is no mandatory prerequisite for issuance of a Section 21 notice prior to the commencement of Arbitration. Issuance of a Section 21 notice may come to the aid of parties and the arbitrator in determining the limitation for the claim. Failure to issue a Section 21 notice would not be fatal to a party in Arbitration if the claim is otherwise valid and the disputes arbitrable.”
“In our opinion, the High Court totally erred in setting aside the award on the basis that the appointment of the Tribunal was only to adjudicate dispute No.1. The High Court also erred in holding that the non-issuance of notice under Section 21 of the A&C Act by the appellant with regard to dispute no. 2 to 4 was fatal for it to pursue its claim before the arbitrator.”
“In the present case, we have already held that the rigors of clause 24, 24.1 and 25 have not been followed by the parties and by their conduct the entire dispute have been thrown at large before the Arbitral Tribunal. Hence, the contention of the respondent that the case of the parties is governed by para 41(c) of Praveen Enterprises (supra) is rejected.”
Provisions interpreted
Case and bench
- Parties
- M/s Bhagheeratha Engineering Ltd. v. State of Kerala
- Case
- Civil Appeal No. 39 of 2026 (arising out of Special Leave Petition (Civil) No. 7338 of 2025)
- Decided
- 5 January 2026
- Bench
- J.B. Pardiwala, K.V. Viswanathan
- Opinions
- Unanimous. Judgment of the Court delivered by K.V. Viswanathan J.